Photos » 2 X 125 MW SLPP Expansion Project » Phase II Album » November 2009
Lignite handling system -one stream commissioning completed and lignite firing done on 29.11.2009 Unit-3 Cooling Tower commissioning work completed Unit-3 Synchronisation achieved on 29.11.2009