2 X 125 MW Expansion Project
 
Surat Lignite Power Plant's 2 X 125 MW expansion project is awarded to M/s BHEL on EPC basis. Commercial operation of the Units are scheduled by November 2008 and March 2009. The construction jobs are progressing on schedule.

Phase II-Archives

June 2008

 
Raw Water Reservoir Sand Filling Work, Geo-Membrane Sheet Laying, PCC & RCC Work Under Progress Lignite Handling Stacker Reclaimer Rail Beam Civil Work Under Progress Lignite Handling -Fabrication Work Under Progress
CW Pump House Civil Work Under Progress TG Bldg Structure Erection Work Under Progress Unit-4 Cooling Tower Civil Work Under Progress
Unit-3 Cooling Tower Civil Work Under Progress Unit-3 BFP Erection Work Under Progress Unit-3 Condenser Erection Work Under Progress
Unit-4 ESP Erection Work Under Progress Unit-4 Boiler Erection Work Under Progress Unit-3 ESP Erection Work Under Progress
Unit-3 Boiler Erection Work Under Progress
 

May 2008

 
Lignite Handling Stacker Reclaimer Rail Beam Civil Work Under Progress Raw Water Reservoir Sand Filling Work, Geo-membrane Sheet Laying, PCC & RCC Work Under Progress Unit-4 Cooling Tower Civil Work Under Progress
Unit-3 Cooling Tower Civil Work Under Progress Chimney RCC Shell Work Completed on 19/04/2008 Unit-4 TG Deck Casting Work Completed on 19/04/2008
TG Building Structure Erection Work Under Progress Unit-3 Condenser Erection Work Under Progress Unit-4 ESP Erection Work Under Progress
Unit-4 Boiler Erection Work Under Progress Unit-3 ESP Erection Work Under Progress Unit-3 Boiler Erection Work Under Progress
 

April 2008

 
Unit-3 Boiler erection work under progress Unit-3 ESP erection work under progress Unit-4 Boiler erection work under progress
Unit-4 ESP erection work under progress Unit-3 Condenser erection work under progress TG Bldg structure erection work under progress
 
Unit-4 TG Deck shuttering work under progress Chimney civil work under progress Unit-3 Cooling tower civil work under progress
CWPH reinforcement and shuttering work under progress Raw water reservoir Sand filling work, Geo-membrane sheet laying, PCC & RCC work under progress Lignite handling stacker reclaimer form work for rail beam work under progress
 
Bed ash silo civil work under progress Fly ash silo civil work under progress
 

March 2008

     
Unit-3 Boiler Erection work under progress Unit-3 ESP erection work under progress Unit-4 Boiler Erection work under progress
 
Unit-4 ESP erection work under progress Unit-3 TG Deck work completed and TG Bldg structure erection work under progress Chimney RCC shell work under progress
 
Cooling Tower Unit-3 Pedestal work under progress CW Chnnel RCC work under progress CW Pump House excavation work under progress
 
Fly ash silo pedestal work under progress Lignite handling stacker reclaimer pedestal work under progress Raw water reservoir sand filling and PCC work under progress
 

February 2008

     
Chimney Slip form Shuttering work under progress CW forebay channel civil work under progress Fly ash silo civil work under progress
 
Raw water Reservoir Sand filling work, Geo-membrane sheet laying and PCC work under progress SLPP Phase II Expansion Project- Panoramic view- Boiler area Switchyard Tower foundation civil work completed & backfilling and cable trench work under progress
 
 
TG building Columns, Beams,Truss work under progress Unit -3 Cooling Tower -civil work under progress  
 

January 2008

     
Chimney Slip form Shuttering work under progress Fly ash silo raft work under progress SLPP Phase II Expansion Project- Panoramic view- Boiler area
 
Switchyard Tower foundation civil work completed & backfilling under progress TG building Columns, Beams,Truss work under progress Unit-3 TG Building Columns, Beams,Truss work under progress
 
 
Unit -3 ESP erection work under progress Unit -3 Cooling Tower Excavation work under progress  
 

December 2007

     
 
Unit-4 Boiler Drum lifting activity Unit-4 Boiler Drum lifted position  
 

November 2007

     
250 MT Crane in operation Panoramic view Boiler & ESP Unit-4 Boiler erection work under progress
 
Unit 3 Boiler APH erection work under progress Unit 3 Boiler Cyclone assembly work under progress Unit 3 Boiler erection work under progress
 
   
Unit 3 ESP erection work under progress    
 

October 2007

     
SLPP Phase II Expansion Project - Boiler Area Panoramic view Unit-3 Boiler erection work under progress Unit-4 Boiler erection work under progress
 
Unit-3 ESP erection work under progress Unit-4 ESP erection work under progress Unit-3 & 4 - Turbine area Civil work under progress
 
 
TG Building Columns Structure fabrication work under progress Switchyard civil work under progress  
 

September 2007

     
SLPP Phase II Expansion Project - Boiler Area Panoramic view TG Building Columns Structure fabrication work under progress Unit-3 & 4 - Turbine area Civil work under progress
 
Unit-3 Boiler erection work under progress Unit-3 ESP erection work under progress Unit-4 Boiler erection work under progress
 
 
Unit-4 ESP erection work under progress Unit-3 Boiler erection work under progress  
 

August 2007

     
Unit-3 Boiler Drum lifting (Major Milestone) completed on 25.08.2007 Unit-3 Boiler Drum lifting under progress Unit- 3 Boiler Drum lifting under process
 
TG Building Columns Structure fabrication work under progress TG Building Columns Structure fabrication work under progress SLPP Phase II Expansion Project - Boiler Area Panoramic view
 
Unit-3 & 4 - Turbine area Civil work under progress Unit-3 Boiler & ESP Erection work under progress Unit-3 ESP Erection work under progress
 
 
Unit-4 Boiler Erection work under progress Unit-4 Drum received at SLPP site on 30.07.2007  
 

July 2007

     
SLPP Phase II Expansion Project - Boiler Area Panoramic view TG Building Columns Structure fabrication work under progress Unit-3 & 4 - Turbine area Civil work under progress
 
Unit-3 Boiler & ESP Erection work under progress Unit-3 Boiler Fifth Tier Erection work under progress Unit-3 ESP Erection work under progress
 

Phase II-Archives