2 X 125 MW Expansion Project
 
Surat Lignite Power Plant's 2 X 125 MW expansion project is awarded to M/s BHEL on EPC basis. Commercial operation of the Units are scheduled by November 2008 and March 2009. The construction jobs are progressing on schedule.

Current Photos

June 2007

     
SLPP Phase II Expansion Project - Panoranic view - Unit-3 Boiler & ESP Switchyard area excavation work under progress Switchyard area excavation work under progress
 
TG Building Column foundation work under progress TG column Structure fabrication work under progress TG column Structure fabrication work under progress
 
TG raft Unit_3 & 4 completed, Power house Main Bldg footing under progress Unit-3 Boiler Erection under progress Unit-3 ESP Erection under progress
 
Unit 3 Boiler Erection Unit 3 Boiler Erection under progress Unit 3 ESP Erection under progress
 
   
Unit 3 Boiler fourth tier Erection under progress    
 

May 2007

     
Panoramic view - 1st May 2007 Turbine Bldg column concreting work in progress - 1st May 2007 Unit-3 Boiler Erection work in progress - 1st May 2007
 
Unit 3 Boiler Erection work in progress - 1st May 2007 Unit 3 ESP Erection work in progress - 1st May 2007 Unit 3 Turbine-Generator(TG) raft concreting work completed - 1st May 2007
 
 
Unit 3 & Unit 4 Turbine area work under progress - 1st May, 2007 Unit 4 Turbine area PCC work under progress - 3rd May, 2007  
 

March 2007

     
SLPP Expansion Unit 3
Boiler Drum Dispatch from BHEL-Trichy as per Schedule on 29th March 2007
Unit-4 ESP Foundation work under progress - 27th March, 2007 Unit-4 Boiler Foundation work back-filling work under progress - 27th March, 2007
 
Unit-3 ESP Foundation work nearly completion  - 27th March, 2007 Unit - 3 First Tier Boiler erection under progress - 27th March, 2007 Unit- 3 Boiler Erection under progress - 27th March, 2007
 
Unit-3 TG reinforcement work under progress - 27th March, 2007 Unit 3 TG reinforcement work under progress - 27th March, 2007 Unit 3 Boiler Erection- First Tier in progress - 8th March, 2007
 
Unit-3 TG excavation under progress - 8th March, 2007 Site - Panoramic View - 6th March, 2007 Unit 3 Boiler Erection First Tier in progress - 6th March, 2007
 
   
Material Storage - 6th March, 2007    
 

January 2007

 
Site - Panoramic View - 31st January, 2007 Unit 4 Boiler Foundation Reinforcement, Form Work of Pedestal Under Progress - 31st January, 2007 Unit - 3 ESP Foundation reinforcement Under Progress - 31st January, 2007
 
Unit - 3 Boiler Back Filling Under Progress - 31st January, 2007 Unit 4-Boiler  Foundation work under progress - 31st January, 2007 Unit 3-Boiler Foundation nearing completion - 31st January, 2007
 

Current Photos