Plant Performance


250 MW Surat Lignite Power Plant Phase-II
| Parameter |
Unit |
Q3 FY 25-26 |
FY 25-26 |
FY 24-25 |
FY 23-24 |
FY 22-23 |
| Generation |
MUs |
426.86 |
1199.98 |
1651.15 |
1616.71 |
1538.18 |
| PLF |
% |
77.33 |
72.73 |
75.40 |
73.62 |
70.24 |
250 MW Surat Lignite Power Plant Phase-I
| Parameter |
Unit |
Q3 FY 25-26 |
FY 25-26 |
FY 24-25 |
FY 23-24 |
FY 22-23 |
| Generation |
MUs |
386.80 |
1114.48 |
1513.63 |
1468.34 |
1366.06 |
| PLF |
% |
70.07 |
67.54 |
69.12 |
66.86 |
62.38 |
165 MW Combined Cycle Power Plant
| Parameter |
Unit |
|
| Generation |
MUs |
Station is in-operative since December 2020. |
| PLF |
% |
145 MW Combined Cycle Power Plant
| Parameter |
Unit |
|
FY 21-22 |
| Generation |
MUs |
Station is in-operative since November, 2021. |
212.81 |
| PLF |
% |
16.75 |
Solar
| Parameter |
Unit |
Q3 FY 25-26 |
FY 25-26 |
FY 24-25 |
FY 23-24 |
FY 22-23 |
| Installed Capacity |
MW |
937.00 |
937.00 |
262.00 |
262.00 |
262.00 |
| Net Energy Injected into Grid |
MUs |
287.27 |
609.86 |
526.43 |
536.04 |
525.01 |
| CUF |
% |
18.40 |
18.94 |
22.94 |
23.29 |
22.88 |
Note: 600 MW Khavda Solar Power Plant commissioned in Phases in the period June-December, 2025. 75 MW Vastan Solar Power Plant commissioned in June, 2025.
Wind
| Parameter |
Unit |
Q3 FY 25-26 |
FY 25-26 |
FY 24-25 |
FY 23-24 |
FY 22-23 |
| Installed Capacity |
MW |
112.40 |
112.40 |
112.40 |
112.40 |
112.40 |
| Net Energy Injected into Grid |
MUs |
35.40 |
154.04 |
170.38 |
209.32 |
215.60 |
| CUF |
% |
14.26 |
20.77 |
17.30 |
21.20 |
21.90 |